Summary
A sanitary sewer main near the east end of Poplar Grove Drive has been exposed by creek erosion and needs protecting. Council hired Choice One Engineering to design the fix, with construction planned for 2027.
At a glance
- Total mentions
- 2
- Last 30 days
- 0
Last discussed May 18, 2026.
Impact analysis
$55,400 for design now, with construction budgeted in the 2026 Capital Improvement Budget for 2027.
Residents near Poplar Grove Drive and everyone who relies on the sanitary sewer system avoid a potential sewer failure.
Mentions & discussions (2)
City Council (Regular) - May 18, 2026
A sanitary sewer main near the east end of Poplar Grove Drive has been exposed by creek erosion and needs protecting. Council hired Choice One Engineering to design the fix, with construction planned for 2027.
City Council (Work) - May 4, 2026
A 1963 sewer line near Poplar Grove Drive has been exposed by creek erosion and needs engineering protection work, with construction planned for 2027.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Vandalia
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.